The Consequences of Indifference in Managing a Construction Project

A contract is meant to outline the scope of work, obligations, allocation of risk, and legal rights of both parties on a construction project.  We have all heard the occasional story of a contractor that promises to have work complete by a date certain but does not show up very often and ends up completing the project late.  The consequences for failing to effectively manage a construction project, however, can be significant and costly.   

 

A properly prepared contract will address the issue of damages when there are delays on a project.  There are various means of addressing the issue of late completion and the allocation of damages for failing to meet a substantial completion date.  In particular, one way is to limit the amount of damages for breach of contract. 

 

In construction contracts it is common to include a waiver of consequential damages provision.  Consequential damages are damages that result indirectly from the act that amounts to a breach of contract.  Depending on the circumstances, lost profits can be considered consequential damages that are recoverable.  Even where the parties attempt to waive consequential damages, such damages still may be recoverable depending on the wording of the contract.  The actions of the parties during the performance of the project can make a difference.   

 

The issue of a contractor’s responsibility for managing a construction project and failing to meet its substantial completion date was recently addressed in the 2nd District Court of Appeals, Case Nos. 28767, 28768, 2021-Ohio-13 (the “Tavern Case”).

 

Case Facts


In the Tavern Case, an owner of a tavern hired a contractor to remodel a property for a new tavern.  The owner conveyed to the contractor on multiple occasions that the work needed to be complete prior to the fall holiday season because of the amount of business expected during this period.  The contractor made promises that it could meet the owner’s schedule for project completion. 

 

During the work, the owner made multiple payments to the contractor for work related to design, supplies, and demolition.  Near the time demolition began, however, the representative for the contractor took a vacation and work did not progress.  Notably, the contractor had not submitted the plans for permitting or coordinated this to be done in his absence.  The owner submitted the plans.  The owner also expressed concern that work was not getting done and, when the owner performed site visits, crews were not working. 

 

By October, it was clear the work would not be completed on time.  The parties to the contract executed a change order to extend the substantial completion date to early December. 

 

The contractor failed to progress the work to meet the new substantial completion date set for early December.  Notably, the contractor took another extended vacation over Thanksgiving.  The owner attempted to contact the contractor because work was not progressing, but the contractor was unresponsive to texts.  By the early December substantial completion date, the work was such that dry wall was not installed and the electrical and plumbing work was only roughed in.

 

The project was eventually completed, but well past the substantial completion date. 

 

The parties both filed various claims against each other related to the Project.  The contractor was seeking payment for amounts it alleged was owed.  The owner generally sought damages related to the late completion.  The trial court held that the owner did indeed owe the contractor for costs related to work performed outside of the contract.  But the court also held that the contractor breached the contract by failing to meet the substantial completion date and did so in a reckless manner, which opened the door to the contractor’s responsibility for consequential damages, including the award of lost profits.

 

Both parties appealed.  The contractor argued that it did not breach the contract because the owner was responsible for delays at the beginning of the project and the contractor was substantially complete by the substantial completion date.  The contractor further argued that it did not perform in a reckless manner as it acted diligently and was hampered by the owner’s early delays.  Moreover, the contractor argued that even if there was a breach of contract due to late completion, there was a waiver of consequential damages provision in the contract and the owner should not be entitled to lost profits. 

 

Delay When Time is of the Essence

 

The trial court determined that time was of the essence for the completion of the project based on the sense of urgency conveyed by the owner to the contractor.  As to why the project was not completed on time, there appeared to be finger-pointing as to who was responsible for delay in the beginning of the project with allegations by the contractor that the owner was responsible for various delays.  The Court, however, did not lend credence to claims that the owner caused delay and did not go into detail on these issues because the parties executed a change order after these alleged events to move the substantial completion date to early December.

 

The Court of Appeals agreed stating that time was of the essence in this contract because the contractor was aware of the pressing need to open the tavern before the holidays, the suspension of the owner’s rental payments based on a September opening, and the contractor was aware that there was much work remaining at the time of the change order.   

 

As to whether the contractor was substantially complete by the December substantial completion date, the Court looked to a statutory definition of substantial completion, case law and the evidence at trial to conclude that there was clearly a significant amount of work remaining on the December substantial completion date and the work was not completed until February. 

 

Indifference as Recklessness


In response to the contractor’s argument that it was not reckless, the Court examined Ohio law as it relates to reckless conduct.  The Court cited to a Supreme Court case providing that “[r]eckless conduct is characterized by the conscious disregard of or indifference to a known or obvious risk of harm to another that is unreasonable under the circumstances and is substantially greater than negligent conduct.”  

 

The Court found that there was credible evidence that the actions of the contractor rose to this level.  The trial court stated that the contractor “failed to substantially complete the work owing entirely to [the contractor representative’s] cavalier and reckless failure to do so, thereby violating the contract’s express provisions…”  The Court agreed, stating the contractor “was aware well before signing the contract that opening the bar quickly was very significant, and he agreed to a time-frame that he then consciously disregarded by going on vacation and by failing to have competent personnel performing the work in his absence.”

 

The Exceptions to a Waiver of Consequential Damages


To avoid the award of lost profits, the contractor pointed to a contract provision that prohibited consequential damages.  That provision, however, provided exceptions to the waiver of consequential damages.  The provision provided an exception for liability that arose from willful or reckless actions.  The Court took no issue with the credibility or the methodology used by the accountant testifying as to the lost profits.  The Court, however, again emphasized that taking vacations without having competent personnel available to manage the project, and continuing to promise completion with knowledge of the urgency for project completion was considered reckless and, therefore, within the exception to permit the award of lost profits as consequential damages.

 

Conclusion


The issues in this case were many, but there are two takeaways.  The language in the contract matters.  It is common for contracts to contain limitations and exceptions in the various provisions, and these should not be taken for granted.  In addition, both owners and contractors must be attentive and responsive to ensure that progress is maintained for the timely completion of any project.